首页 > 数字化转型 > ERP > 【Planning】APO - PPM and PDS from APO

【Planning】APO - PPM and PDS from APO

原创 ERP 作者:edison_tc 时间:2016-12-28 20:40:19 0 删除 编辑

Purpose:

验证: 如果APO里的PPM/PDS没有带R3的PV属性,那么发送过R3的Planning result如PL order,是否可以找到相应的PV呢?

Approach:

Step 1: 手动一个SNP PPM:

Machine generated alternative text:
Display Plan 慏UMMY-84963128-U017? - Multi Display
Delete
L!1[  4jj Functions Activity
Object Type/Object Name Object De.ion Basis
DUMMY-84963128-U017 Plan Number DT.ThQ1Y-84963128-U017 DUMMY-84963128-U017
Operations Operation 0010 Produce
$ 0010:Produce Produce
:j 1O:Placeholder Placeholder
bg Modes  [j gj aj 
Components Activity 10 De.ion Placeholder
Activity Relationships Activity Type 慞 Produce
PPM Scrap (%) 0,000
.  DUMMY-84963128-U017 PLaceholder
Components aMode
Modes
r1 
Mode Primary Resrce Location U... Fix. dur. B... Break w/o... T... t]
____________________ ? 10 D O L
a
&4963128
fla
r - 

 Step 2: 再手工创建一个PDPS PPM


Step 3: PPDS PPM-->SNP PPM


Step 4: check which PPM the Heu. chose..



Send to R3

Machine generated alternative text:
Stock/Requfrements List as of 04:52 .慽rs
Show Overview Tree L  e51 
Material 84963128 BOUNTY 24/9VALUE ADD DES TCH 9OCT BAP
Plant U0171 MRP type X0? Material Type FERT Unit CSH
[t A.. Date MRP ... MRP element data Rescheduli.. E.. Receipt/Reqnt Available Qty Pr...
O8/05/2016 Stock r O
08/10/2016 PlOrd. 1000120030/tck 20 20 0101
08/10/2016 IndReq VSF 20? 0

Machine generated alternative text:
Display Planned Order: Stock order
Components  Components
! LA Stock order i000120030 E Standard in-house
Material 84963128 BOUNTY 24/9VALUE ADD DES TCH 9OCT BAP
Planning Plant U0171 CAPE GIRARDEAU PLANT
// Header L Assignment Master Data Detailed Scheduling Action Contr
Quantities
Order quantity 20 Cs Scrap quantity
Dates/Times
Basic Dates Production Dates Other Dates
End 08/10,20161 ?/09/2016 24:00:00 Available for MRP 08/10/2016
Start 08/08/2016? e/Oe/2Ol6rO7:3O:OOl GRprocessingtime
Opening 108/08/20161
Other Data ______ Firming ________________
Production Plant U0171 flPlanned Order
Storage Location ! ! flCornponents
Production Version H Ca  a c? DIspatch a h
BOM Explosion Number !

它并不反应

lot-size

==> 因为从APO发送给R3,始终是0101的PV,且不reflect Lot-size. 而在R3里的quota等,并不会影响APO--> R3这个过程。


因为如果是M1 MRP type,直接在R3里做planning:

Machine generated alternative text:
[jj Material Num 84963128 BOUNTY 24/9VALUE ADD DES TCH 9OCT BAP
Plant MRP Type Ml Material Type FERT Base Unit Cs
[JA.. Date MRP ... MRP element data Rescheduli... E.. Rec./reqd qty Avail, quantity Pr...
03/05/2016 Stock O
C?/O8I20l6? End of Planning Time Fen...
08/10/2016 [lord. 1000120696/Stole 30 30 0102
08/10/2016IndReqV5F 20? 10

==> 可以看到,qty以及PV,等都是根据R3里的master data来的。


 最后只能使用enhancement来处理:


https://help.sap.com/saphelp_scm50/helpdata/en/07/f474408273d062e10000000a155106/content.htm