It means ending a production order from a logistical viewpoint. This function is usually used, if the execution of an order has to be stopped prematurely or if the order could not be executed in the required manner and open requirements for the order (reservations, capacities) should be deleted.
The following actions are executed if an order is set to Technically complete:
1.The order is not relevant for MRP planning
2.Reservations are deleted
3.Capacity requirements are deleted
4.Purchase requisitions for external operations or non-stock materials are deleted
5.The order and its operations receive the system status Technically Completed (TECO)
Notes:You cannot change the production order. You can however cancel technical completion, if order data has to be changed.