Order split due to following reasons:

1.When partial lot of order is to be handled from the
rest due to quality reasons.
2.If capacity bottle necks exists.
3.Material is commited for part of order qty.

Features:

1.The split operations and the material assigned are
copied into the child order.
2.The structure of the parent order does not changes
while the split off operations are copied into
the child order

Status for parent order : SPLT
Status for the child order: SPLE
For operation : SPLT

Restrictions:

1. The parent order and the child order must be
settled to same cost collector
2.Read PP Master data is not possible
3.Confirmations at header level is not possible

Steps:
1. In OPL8 Set the indicator cost collector
2. Default Rule -Periodic settlement(PP2)
3. CK11N Do std cost estimate
4. KKF6N Create cost collector
5. create prodn order with op10,20,30,40
6. Got op overview
7. Select the op from which you want to split (ex
op20)
8. Goto functions ----> Split order

9. Enter the qty ,if necessary a different order type
for the child order
10 Execute
11.Order will be splitted .

12. The order can be splitted even from op10 itself
13. Goto MD04
14. Two orders will be created
15. Goto op overview of each order and there you can
see the splitting.[@more@]