(527)What is the result of increasing the value of the parameter ASM_POWER_LIMIT during a rebalance operation?

A.The ASM rebalance operation will likely consume fewer resources and complete in a shorter amount of time.

B.The ASM rebalance operation will consume fewer resources and complete in a longer amount of time.

C.The ASM rebalance operation will be parallelized and should complete in a shorter amount of time.

D.There is no ASM_POWER_LIMIT setting used in ASM.

E.None of the above

答案:(C)