原创 IT综合 作者:gugu99 时间:2008-01-30 17:15:48 0 删除 编辑
QUESTION 121
Using Oracle Scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at 9:00 p.m.every Friday.
You want both the jobs to use a single resource plan, WEEKEND_PLAN.
Which task must have already been performed to enable you to achieve this objective?
A. A window must have been created with the WEEKEND_PLAN resource plan.
B. A program must have been created with the WEEKEND_PLAN resource plan.
C. A job class must have been created with the WEEKEND_PLAN resource plan.
D. A windows group must have been created with the WEEKEND_PLAN resource plan.
Answer: A[@more@]