1 check the upper mould parts loosening, attachment on die parts cleaning
Henan Daswell Machinery Co., Ltd,is a professional manufacturer and trader specializing in the research, development and production of construction machinery for nearly 30 years. Our main products are as follows:ready mix concrete plant,SICOMA twin shaft compulsory concrete mixer,block making machine,etc. We will provide you with the best product and service.
2 clean the upper die on the hydraulic cylinder and the surrounding debris diesel cement mixers (for sale), sand, dust. Check whether the loosening of nuts, oil pipe joint is loose.
3 mode synchronous bearing cover and gear loose, to the timely processing of.
4 whether the loosening of vibration transmission.
5 check module parts loosening, clean up the part of the lower die attachment Diesel concrete mixer, pay attention to safety when cleaning, upper and lower die should be on top of block.
6 the press rod nut loosening, timely adjustment of locking.
7 mold cylinder and beam connectors and fasteners, pipe joint is loose.
8 vibration plate groove ned debris to clear.
9 check processing under the vibration transmission parts and the pipe joint is loose.
10 check the upper and lower die proximity switch position whether to have the change, the limiting block is firm concrete mixing plant, otherwise it should timely adjust.