At the core of the issue is the System Change Number (SCN) in Oracle.
This is a number that increments sequentially with every database
commit: inserts, updates, and deletes. The SCN is also incremented
through linked database interactions.
The SCN is crucial to
normal Oracle database operation. The SCN "time stamp" is the key to
maintaining data consistency in Oracle, allowing the database to respond
to every user's query with the appropriate version of data at every
point in time. It functions as the database's clock, so to speak. And
like time, the SCN cannot decrement. It must always tick forward.
When
Oracle databases link to each other, maintaining data consistency
requires them to synchronize to a common SCN. This is necessarily the
highest SCN carried by any participating Oracle database instance
because the SCN clock cannot run backward -- so database linking causes
the SCN in many databases to jump during normal operations. And only
very basic permissions are required to make a connection that can cause
one database to increment the SCN on another.
The architects of
Oracle's flagship database application must have been well aware the SCN
needed to be a massive integer. It is: a 48-bit number
(281,474,976,710,656). It would take eons for an Oracle database to
eclipse that number of transactions and cause problems -- or so you
might think.