I was a fortunate young developer. In my first three months at
work, I ran into the 90% done schedule game. I did it to myself.I
estimated a particular task was going to take 6 weeks. Of course,
being an arrogant and naive developer, it never occurred to me to
break the task down into inch-pebbles. (That would have told me
whether I even knew what to do for the task.)
At the end of the first week, I was 20% done. At the end of the
second week, I was 40% done. At the end of the third week I was 60%
done. At the end of the fourth week, I was 80% done. Right on time,
at the end of the fifth week, I was 90% done. At the end of the
sixth week, I was 92% done. Seventh week, 93% done. Time and I both
marched onward. At the end of the 10th week, I was 97% done. But
this time, I actually believed I was within a week of being done --
I only had three one-day tasks left to complete. It took me two
more weeks. A total of 12 weeks for a 6 week task.
(一个大粒度的任务到达个人后,对于个人一定要认为这个大粒度的任务就是一个完整的项目,要有计划,有WBS分解,有相应的里程碑和检查点。不要太狂妄自大和天真,不要太相信自我的经验和直觉,特别是对于复杂的问题,周期跨度较长的项目我们的经验和直觉往往会失效。在这里我们会再次强调挣值的0-100法则,对于一件事情及时你反馈完成99%,但是只要没有100%完成,没有通过最后的验收你仍然得不到一丝的报酬。90%完成也是一种进度欺骗,可能是你欺骗
了你的领导,也可能是你欺骗了自己,你自己的经验和你开了一个玩笑。看上面作者的例子可以看到,一个估算为6周的工作,完成90%的时候花费了6周,而完成最后的10%又花费了6周。)
During the time I was 92%, 93%, 94% done, I wrote status reports to
my manager, explaining I'd run into unanticipated problems and that
I hadn't estimated all the things I needed to do. He was lovely
about it, and kept saying, "Ok, let me know your updated
estimate."(不知道大家有没有做一件事情或任务,做到后面越做越复杂的体会。出现这种问题的原因不仅仅是估算不足或者是风险管理没有做好。这是一个涉及到个人计划和任务管理的一个复杂的系统问题。)
At the end of this task, when I was finally done, he was all set to
move on. I told him I would be estimating differently from now on,
with much more detail, and several deliverables each week. If I
couldn't give him a date to be done, was that ok with him. We
talked and I agreed to supply a date with a risk factor with each
estimate.
I wish I could tell you I became a perfect estimator then. I
didn't. I'm still learning to estimate. But I now know that when I
think I'm 90% done, I'm probably only 50% done.
(根据经验你任务90%的任务完成而实际情况往往只是完成了50%的工作任务。90%的任务完成改进的焦点在估算方法和风险管理两个方面,而估算方法的改进首先则是要有一个完善的WBS工作任务分解。)
I'm not the only one. The 90% done schedule game can occur under
any conditions: reasonable or unreasonable schedule, low or high
risk technology. 90% done is about our ability to predict the
future, to perform accurate estimation, and to understand -- in
advance -- if we will be interrupted. Not a trivial problem.
The 90% done schedule game is the reason I like feedback during
project work, in the form of inch pebble estimation, one-on-one
meetings with managers, visible project status, and project-wide
rolling wave planning.
(如何解决90%任务完成的问题,作者在文章开始就已经指出了具体的方法,即break
the task down into
inch-pebbles。即要把一个大的工作任务分解为一个个的细粒度的子任务,在分解为子任务的过程中有两个核心要素是需要强调的,第一个是每个子任务都需要有明确的产出物进行验收;第二个是我们强调的是迭代而不是增量,因此任务切分的方式是横向的而不是纵向的。举例来说如果一个软件开发有10个较为独立的功能点要做,则我们需要的分解是每各个功能点什么时候能够全部完成需求,开发和测试。如果你的分解方式是10个功能点都完成需求,都完成设计等,这种子任务的分解方式对我们来说仍然是属于进度不明朗。计划和任务管理和我们平时做事情的思维模式是一样的,所有任务都去做一点还不如一件事情一件事情的做完做好。)