456.Which of the following is true about job chains?
A. They consist of one or more Scheduler programs.
B. They are used to implement dependency scheduling.
C. They are used to implement time-based scheduling.
D. They are used to implement event-based scheduling.
E. None of the above.
Answer: B


既然是chain, 那就应该有dependency才合理.

A chain is a named series of tasks that are linked together for a combined objective. Chains are the means by which you can implement dependency based scheduling, in which jobs are started depending on the outcomes of one or more previous jobs.

To create and use a chain, you complete these tasks in order:


官方文档:https://docs.oracle.com/cd/B28359_01/server.111/b28310/scheduse009.htm

来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/8520577/viewspace-2074999/,如需转载,请注明出处,否则将追究法律责任。

请登录后发表评论 登录
全部评论
曾从事java方向开发多年。近年已经转入数据库方向。主要擅长SQL优化,Oracle数据库问题诊断,Oracle备份与恢复等。服务于医药物流,医院等行业

注册时间:2010-01-26

  • 博文量
    556
  • 访问量
    841672